Optimizing Cost Management: A Case Study in Process Costing at Howard and Sons Construction Inc.

QUESTION

Train A, traveling 40 mph, leaves Westford heading toward Eastford, 260 miles away. One hour after Train A leaves Westford, Train B, traveling 70 mph, leaves Eastford heading toward Westford. If you could only watch one TV show for the next year, what would it be? 2)Below is the cost information related to maintenance costs for the past three months: Month Units Produced Total Cost August 2,400 $ 14,800 September 1,450 $ 12,300 October 3,600 $ 21,100 a. Using the high-low method, calculate the fixed cost per month and variable cost per unit. b. What would the total maintenance costs be for a month with 2,400 units produced? 3)The following information related to the work-in-process balance for Howard and Sons Construction Inc. as of June 1st: Beginning work in process (units) 50,000 Direct materials in beginning work in process $ 230,000 Conversion costs in beginning work in process $ 193,000 The following data relate to activity during the month of June: Units started 70,000 Production completed (units) 80,000 Direct materials used $450,000 Conversion cost $635,000 The company uses a weighted-average process-costing system. All materials are added at the start of manufacturing; in contrast, conversion cost is incurred evenly throughout production. At the end of the month, work in process is 100% complete with respect to direct materials and 70% with respect to conversion costs. Required: A. Compute the total equivalent units for direct material and conversion cost. B. Compute the cost per equivalent unit of direct material and conversion cost. C. Determine the cost of completed production. D. Determine the cost of the June 30th work in process.

ANSWER

Optimizing Cost Management: A Case Study in Process Costing at Howard and Sons Construction Inc.

Process costing is a crucial aspect of managing the costs associated with manufacturing and production in various industries. To gain a deeper understanding of this accounting method, let’s delve into a case study involving Howard and Sons Construction Inc. This company employs a weighted-average process-costing system, which is used to determine the cost of work in process, production completion, and the overall cost of production.

Compute the Total Equivalent Units for Direct Material and Conversion Cost

The total equivalent units are essential to gauge the work-in-process balance accurately. In the case of Howard and Sons Construction Inc., they began the month with 50,000 units in work in process. During the month, they started 70,000 units and completed 80,000 units. To calculate the equivalent units for direct material, we subtract the production completion from the sum of units started and the beginning work in process:

Equivalent units for direct material = Units started + Beginning work in process – Production completed Equivalent units for direct material = 70,000 + 50,000 – 80,000 = 40,000 units

For the conversion cost, we take into account the percentage of completion with respect to conversion costs. In this case, they are 70% complete, meaning 70% of the work has been performed:

Equivalent units for conversion cost = Equivalent units for direct material x Percentage of completion with respect to conversion costs Equivalent units for conversion cost = 40,000 units x 70% = 28,000 units

Compute the Cost per Equivalent Unit of Direct Material and Conversion Cost

To calculate the cost per equivalent unit, we divide the total cost by the equivalent units for both direct material and conversion cost.

For direct material, the total cost is $450,000, and the equivalent units are 40,000 units. Therefore:

Cost per equivalent unit for direct material = Cost for direct material / Equivalent units for direct material Cost per equivalent unit for direct material = $450,000 / 40,000 units = $11.25 per unit

For conversion cost, the total cost is $635,000, and the equivalent units are 28,000 units. Hence:

Cost per equivalent unit for conversion cost = Cost for conversion cost / Equivalent units for conversion cost Cost per equivalent unit for conversion cost = $635,000 / 28,000 units ≈ $22.68 per unit

Determine the Cost of Completed Production

The cost of completed production represents the total cost incurred for the units that were completed during the month. In this case, 80,000 units were completed. To find this cost, we sum the cost of direct material and conversion cost for these units:

Total cost of completed production = Cost per equivalent unit for direct material x Equivalent units for direct material completed + Cost per equivalent unit for conversion cost x Equivalent units for conversion cost completed Total cost of completed production = ($11.25 x 80,000) + ($22.68 x 80,000) Total cost of completed production = $900,000 + $1,814,400 Total cost of completed production = $2,714,400

Determine the Cost of the June 30th Work in Process

The cost of the June 30th work in process represents the cost incurred for the units still in progress at the end of the month. In this case, there are 50,000 units in work in process. They are 100% complete with respect to direct materials and 70% complete with respect to conversion costs. To find this cost, we need to consider both the direct material and conversion cost:

Cost of work in process = Cost for direct material (100% complete) + (Cost for conversion cost (70% complete) / 100%) Cost of work in process = $230,000 + ($22.68 x 50,000 x 0.70) Cost of work in process = $230,000 + $794,400 Cost of work in process = $1,024,400

In conclusion, process costing, as exemplified by the case of Howard and Sons Construction Inc., is a systematic method for calculating costs in a manufacturing environment. By accurately determining equivalent units and costs per equivalent unit, it becomes possible to efficiently manage production expenses and make informed business decisions. The knowledge of work-in-process balance, cost of completed production, and the cost of ongoing work in process is invaluable in optimizing financial control within any manufacturing industry.

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 Customer support
On-demand options
  • Tutor’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Attractive discounts
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Unique Features

As a renowned provider of the best writing services, we have selected unique features which we offer to our customers as their guarantees that will make your user experience stress-free.

Money-Back Guarantee

Unlike other companies, our money-back guarantee ensures the safety of our customers' money. For whatever reason, the customer may request a refund; our support team assesses the ground on which the refund is requested and processes it instantly. However, our customers are lucky as they have the least chances to experience this as we are always prepared to serve you with the best.

Zero-Plagiarism Guarantee

Plagiarism is the worst academic offense that is highly punishable by all educational institutions. It's for this reason that Peachy Tutors does not condone any plagiarism. We use advanced plagiarism detection software that ensures there are no chances of similarity on your papers.

Free-Revision Policy

Sometimes your professor may be a little bit stubborn and needs some changes made on your paper, or you might need some customization done. All at your service, we will work on your revision till you are satisfied with the quality of work. All for Free!

Privacy And Confidentiality

We take our client's confidentiality as our highest priority; thus, we never share our client's information with third parties. Our company uses the standard encryption technology to store data and only uses trusted payment gateways.

High Quality Papers

Anytime you order your paper with us, be assured of the paper quality. Our tutors are highly skilled in researching and writing quality content that is relevant to the paper instructions and presented professionally. This makes us the best in the industry as our tutors can handle any type of paper despite its complexity.